McLaren Construction Midlands and North is continuing to make strong progress on the TJ Morris Distribution Centre in Doncaster, with significant structural, envelope and internal milestones now achieved.

The steel frame for the development was completed in November, with ground floor slab works also commencing the same month. The building is on track to become fully watertight by the end of February, with cladding works progressing well and targeted for completion in the Spring.

Significant progress has also been made on the Vehicle Maintenance Unit (VMU) with the steel structure now fully erected, approximately 90% of the cladding installed and the fit out of the internal workshop scheduled to commence in March.

Externally, a major milestone will also be reached in late March with the completion of the base course tarmac to the external hard standing areas. Internally, office fit-out works across the ground, first and second floors will begin in early February, delivering modern office accommodation alongside a commercial kitchen and canteen.

Within the warehouse, high-level mechanical and electrical services installation is nearing completion, including the sprinkler system. Once slab works are finalised, teams will return to bring internal levels up to finished ground level. Specialist industrial freezer works are scheduled to commence in the spring.